National Grid - Capacity Market Rules change proposal 23

Change Proposal
Publication date

This proposal from National Grid seeks to clarify whether a prequalification application should be considered if an opt-out decision has previously been submitted. Amendments to Rules 3.3.3 (b) and 4.2.3 are proposed. National Grid have suggested that implementation of this proposal may be delayed until after the 2015 prequalification process.

Change proposal status
Closed (accepted)

Proposal rules area

  • Determination of eligibility
  • Prequalification Information

Proposal organisation

National Grid Electricity Transmission