EP Invest Ltd - Capacity Market Rules CP228

Change Proposal
Publication date

This proposal would amend 13.4.1 so that, where a CMU that has failed to demonstrate satisfactory performance during the Delivery Year, for example due to a Unit breaking-down, a CMU will have its Capacity Obligation and Payments reduced to reflect the third highest net output demonstrated in the relevant Delivery Year. The proposed amendment is suggested to ensure that the remaining Units within a CMU are still incentivised to meet CM Obligation during the Delivery Year.

Change proposal status
Closed (rejected)

Proposal rules area

Testing Regime

Proposal organisation

EP Invest