Energy UK – Capacity Market Rules CP126

Change Proposal
Publication date

This proposal from Energy UK would clarify that when a Refurbishing CMU’s connection capacity is equal its Pre-Refurbishment connection capacity, it does not have to be issued with a Final Operational Notification (FON) or an Interim Operational Notification (ION) for it to be classed as ‘Operational’. It would also remove the requirement for this type of CMU to notify the Delivery Body when an FON or ION is issued.

Change proposal status
Closed (accepted)

Proposal rules area

  • Capacity Agreements
  • General Provisions

Proposal organisation

Energy UK