Energy Company Obligation public reports and data

Energy Company Obligation public reports and data

Energy Company Obligation 3 interim measures

The Energy Company Obligation 4 order commenced on 27 July 2022 and will run to 31 March 2026. Measures delivered between 1 April 2022 to 26 July 2022 will contribute to Energy Company Obligation 4 delivery and will be known as Energy Company Obligation 3 Interim measures as they are delivered in accordance with Energy Company Obligation 3 regulations.

Suppliers had to notify us of any Energy Company Obligation 3 interim measures installed between 1 April 2022 and 26 July 2022 by the end of September 2022.

Any Energy Company Obligation 4 measures completed between 27 July 2022 and 31 July 2022 also had to be notified by the end of September 2022.

Any measures completed on or after 1 August 2022 must be notified by the end of the month following the month in which installation of a measure was completed.

Energy Company Obligation 4 development

The following data tables have been added to this page:

  • overall progress towards Heating Home Cost Reduction Obligation, Solid Wall Minimum Requirement, EFG Minimum Requirement and Flex cap
  • Heating Home Cost Reduction Obligation by supplier

Further data will be made available in coming months.

Progress towards Obligation

Progress towards Phase 1, 2 and 3

To achieve its ECO obligations, a supplier must install measures that qualify under the scheme and deliver annual bill savings for the household.

ECO4 sets a main obligation called the Home Heating Cost Reduction Obligation (HHCRO), which requires energy suppliers to achieve a total of £224.3 million in annual bill savings for domestic premises by 31 March 2026.

The obligation is divided between energy suppliers based on their respective shares of the domestic gas and electricity market.

A supplier meets its obligations under ECO4 by promoting qualifying actions (‘measures’) at eligible domestic premises, and must do so in full no later than 31 March 2026.
           
The overall obligation period for ECO4 runs from the commencement of the ECO4 Order on 27 July 2022 to 31 March 2026 and is split into four phases:

•    Phase 1: 27 July 2022 to 31 March 2023
•    Phase 2: 1 April 2023 to 31 March 2024
•    Phase 3: 1 April 2024 to 31 March 2025
•    Phase 4: 1 April 2025 to 31 March 2026

A supplier’s total obligation is determined by adding together their obligations for each phase. They must meet their total obligation by the end of 31 March 2026.

Measures

Notified Energy Company Obligation 4 measures by category

The table below shows the measures submitted to Ofgem as of 11 November 2024.

This does not include Energy Company Obligation 4 measures that have been notified as exemption measures. For further details on exemption measures, please refer to: Energy Company Obligation (ECO4) Guidance: Delivery

Measure Type Surplus Actions ECO3 Interim ECO4 Total
Boiler - Repair of an efficient heating system 0 0 0 0
Boiler - Replacement of a broken efficient heating system 1,847 1,804 209 3,860
Boiler - Upgrade of an efficient heating system to a renewable heating system 0 0 20,368 20,368
Boiler - Upgrade of an inefficient heating system 4 1 49,789 49,794
Boiler - Upgrade to Unknown* - - 1 1
Cavity Wall Insulation 13,724 12,720 20,628 47,062
District Heating Connection  0 2 1,309 1,311
ESH - Repair of a broken efficient ESH - - 0 0
ESH - Replacement of a broken efficient ESH 0 0 0 0
ESH - Upgrade of an inefficient heater 1,749 1,723 3,830 7,302
First time central heating to a non-renewable heating system 2,775 1,802 10,127 14,704
First time central heating to a renewable heating system 32 72 8,552 8,656
First time central heating to an unknown heating system* - - 0 0
Heating controls 15,809 5,168 306,093 327,070
Loft Insulation 11,883 4,038 71,487 87,408
Other Insulation** 100 35 3,485 3,620
Park Home Insulation 29 0 687 716
Room-in-roof Insulation 946 290 11,745 12,981
Solar PV 138 103 33,569 33,810
Solid Wall Insulation 6,956 1,571 48,833 57,360
Underfloor Insulation 4,703 896 1,320 6,919
Grand Total 60,695 30,215 592,032 682,942

Table commentary

A total of 143,555 Energy Company Obligation 4 projects have been submitted, an increase of 7,925 projects from the previous month.

*A small number of measures have been submitted with an invalid post main heating source for the property, suppliers will be required to update this information

**Other Insulation includes the following measure types – flat & pitched roof insulation, solid floor insulation, window glazing, draught proofing and higher performance external doors. These measures are grouped together given the low delivery volumes.

Publications and updates