P443 - Decision on urgency

Decision
Publication date
Industry sector
Transmission Network

BSC Modification P443 was raised by Saltend Cogeneration Company Limited on 17 August 2022 who requested that it be treated as an Urgent BSC Modification Proposal. This change seeks to Cap NGESO Interconnector Trades at the Value of Lost Load (VoLL). On 18 August 2022, the BSC Panel recommended to Ofgem that P443 should be treated as an Urgent Modification Proposal. We have considered both the Panel’s and the Proposer’s arguments and have decided that P443 should not be progressed on an urgent basis.