National Grid Electricity System Operator Limited (ESO) has written to the Authority to seek a direction pursuant to Standard Licence Condition SLC C27(12)(b) of the Licence, for publication of the NOA report by 31 March 2024 instead of by 31 December 2023.
The ESO has also written to the Authority to seek a direction pursuant to (SLC) C11(1) of the Electricity Transmission Licence, to submit the ETYS appendices by 31 March 2024 instead of by 30 November 2023.
We have decided to direct the ESO to submit its Electricity Ten Year Statement (ETYS) appendices by 31 March 2024 instead of by 30 November 2023, and to publish its Network Options Assessment (NOA) report by 31 March 2024 instead of by 31 December 2023.